Procedures for submission of pavement design plan revisions
Pavement designs for streets within approved site related plans, must be submitted as plan revisions in PLUS. All pavement designs must be signed and sealed by a licensed professional engineer or land surveyor.
Public Streets
Pavement designs for all streets within existing or proposed public right-of-way will be subject to VDOT review, which will generally follow the workflows for plan review outlined in Technical Bulletin 25-07.
When submitting the plan revision in PLUS, the applicant must select “no” to the ESI review field shown below in the PLUS interface.
 Private Streets
Pavement designs for privately maintained streets will be reviewed by Fairfax County, for conformance with the Public Facilities Manual, based on review times described in Technical Bulletin 25-06 corresponding to the timelines associated with a revision to the associated plan (e.g., Site Plan, Rough Grading Plan).
Designated Plans Examiners (DPEs) may request an expedited pavement design review through the Engineering Surveyors Institute (ESI), by selecting “yes” to the ESI review field shown below in the PLUS interface.
 The ESI expedited review is subject to an additional review fee, to be billed by ESI to the applicant directly. The expedited submission must include the following statement signed by the DPE:
This pavement design is in conformance with the requirements of the Fairfax County Public Facilities Manual and is submitted for approval under the Designated Plans Examiner Program.
ESI expedited review will be completed within 2-3 business days.
|