In December 2025, a segment of S. Clark St was closed to southbound traffic to allow the 15th Street S. / S. Clark-Bell Street project team to deliver work in that area. This phase was due to last until early March.
This closure will now extend into Summer 2026 due to utility conflicts encountered. This timeline is contingent on no further conflicts or delays due to weather.
Wait, what's going on on S. Clark Street? Glad you asked. The latest Projects To Watch video from Arlington TV features this key street and trail project to improve the multimodal transportation network in Crystal City.
Tune in below to see what's in store when construction is complete in late 2026.
Rail service at Crystal City Metro station will close starting tomorrow February 14 through Monday, February 16. This work is part of 10 weekend closures to allow work on the Crystal City East Entrance project to advance safely. Service will resume during the week. There will be no weekend closures during Cherry Blossom season.
Additional rail work by WMATA will also close rail service at Ronald Reagan Washington National Airport Metro and Potomac Yard Metro stations for three of these weekends.
Shuttles will replace trains during rail closures.
|